ITAC Assessment: UD0565
ITAC logo
ITAC Assessment: UD0565
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product steel hydraulic fittings
NAICS
n/a
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 210
Plant Area 250,000
ft2
Annual Production 6,035
ton
Production Hrs. Annual 5,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $193,468 5,395,076
kWh
Electricity Demand $192,912 30,864
kW-mo/yr
Natural Gas $173,740 41,932
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $489,517 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $103,332

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 4.322: Eliminate old stock and modify inventory control $300,000 $526,500 - - - - - - - - $300,000
02 3.4153: Use counter current rinsing to reduce waste water $95,150 $9,000 $331
15,826
kWh
$227
-
kW-mo/yr
- - - - - $94,592 -
03 4.111: Add equipment/ operators to reduce production bottleneck $27,880 $7,000 - - - - - $2,880 - $25,000 -
04 3.7198: Reduce / eliminate use of disposable product $18,791 $6,000 - - - $13,320
-
gal
- - - $5,471 -
05 3.1163: Use plastic pallets instead of wood $12,625 $25,000 - - - - - - $(-5,000.0) $17,625 -
06 3.5217: Reuse / recycle/ sell paper products $8,240 $6,000 - - - - $8,000
-
lb
$(-3,000.0) $3,240 - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,182 $1,200 $6,290
299,531
kWh
$1,892
-
kW-mo/yr
- - - - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $8,143 $15,231 $2,564
122,216
kWh
$5,579
-
kW-mo/yr
- - - - - - -
09 2.2136: Install / repair insulation on steam lines $6,660 $13,660 - - $6,660
-
MMBtu
- - - - - -
10 2.7121: Utilize daylight whenever possible in lieu of artificial light $3,846 $2,000 $1,500
71,512
kWh
$2,346
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $489,517 $611,591 $10,685
509,085
kWh
$10,044
-
kW-mo/yr
$6,660
-
MMBtu
$13,320
-
gal
$8,000
-
lb
$(-120.0) $(-1,760.0) $142,688 $300,000
TOTAL IMPLEMENTED $103,332 $10,200 $6,621
315,357
kWh
$2,119
-
kW-mo/yr
- - - - - $94,592 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs