| Assessment Year | 1999 |
|---|---|
| Principal Product | Metal castings for electric motors |
| NAICS |
n/a
|
| SIC | 3621: Motors and Generators |
| Sales Range | $500 k to 1M |
| # of Employees | 125 |
| Plant Area |
48,600
ft2
|
| Annual Production | 204,000
lb
|
| Production Hrs. Annual | 3,600
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $40,978 | 1,549,824 |
kWh
|
$0.026 |
| Electricity Demand | $56,393 | 334 |
kW-mo/yr
|
$168.84 |
| Natural Gas | $6,573 | 1,333 |
MMBtu
|
$4.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,475 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,807 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $14,767 | $10,000 |
$4,805
218,347
kWh
|
$9,962
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.3137: Use power during off-peak periods | $10,130 | - | - |
$10,130
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 4.652: Replace existing equipment with more suitable substitutes | $4,200 | $4,000 | - | - | - | - | $4,200 | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,677 | $1,040 |
$1,945
88,511
kWh
|
$3,732
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 3.5111: Filter and reuse hydraulic oil | $5,340 | $4,000 | - | - | - |
$2,984
-
gal
|
- | $2,356 | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,976 | $13,500 |
$4,786
217,761
kWh
|
$9,286
-
kW-mo/yr
|
$(-9,096.0)
-
MMBtu
|
- | - | - | |
| 07 | 3.8143: Recycle cleaning solvent and reuse | $2,344 | $4,000 | - | - | - |
$2,344
-
gal
|
- | - | |
| 08 | 3.5112: Reprocess spent oils on site for re-use | $2,041 | $3,000 | - | - | - |
$1,682
-
gal
|
- | $359 | |
| TOTAL RECOMMENDED | $49,475 | $39,540 |
$11,536
524,619
kWh
|
$33,110
-
kW-mo/yr
|
$(-9,096.0)
-
MMBtu
|
$7,010
-
gal
|
$4,200 | $2,715 | ||
| TOTAL IMPLEMENTED | $15,807 | $1,040 |
$1,945
88,511
kWh
|
$13,862
-
kW-mo/yr
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs