| Assessment Year | 1998 |
|---|---|
| Principal Product | Gray iron & ductile castings |
| NAICS |
n/a
|
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 320 |
| Plant Area |
165,000
ft2
|
| Annual Production | 60,000,000
lb
|
| Production Hrs. Annual | 5,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,826,403 | 47,958,383 |
kWh
|
$0.038 |
| Electricity Demand | $560,729 | 156,192 |
kW-mo/yr
|
$3.59 |
| Natural Gas | $341,077 | 83,518 |
MMBtu
|
$4.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $417,936 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $272,109 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.511: Expand operations into unused space | $237,283 | $1,313,000 | - | - | - | - | $222,750 | $14,533 | - | |
| 02 | 4.652: Replace existing equipment with more suitable substitutes | $123,160 | $115,000 | - | - | - | - | - | - | $123,160 | |
| 03 | 2.2437: Recover waste heat from equipment | $22,667 | $20,000 | - | - |
$22,667
-
MMBtu
|
- | - | - | - | |
| 04 | 3.1161: Eliminate/reduce an operation | $17,490 | - | - | - | - |
$1,890
-
lb
|
- | $15,600 | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $11,454 | - |
$9,925
263,189
kWh
|
$1,529
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,882 | $17,546 |
$5,010
132,181
kWh
|
$872
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $417,936 | $1,465,546 |
$14,935
395,370
kWh
|
$2,401
-
kW-mo/yr
|
$22,667
-
MMBtu
|
$1,890
-
lb
|
$222,750 | $30,133 | $123,160 | ||
| TOTAL IMPLEMENTED | $272,109 | $1,330,546 |
$14,935
395,370
kWh
|
$2,401
-
kW-mo/yr
|
- |
$1,890
-
lb
|
$222,750 | $30,133 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs