ITAC Assessment: UD0554
ITAC logo
ITAC Assessment: UD0554
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Wire ,cold drawn and hot rolled steel, spring, coiling and f
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 210
Plant Area 197,650
ft2
Annual Production 3,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $359,477 8,623,681
kWh
Electricity Demand $112,343 30,528
kW-mo/yr
Natural Gas $274,316 67,355
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $205,151 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,609

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Water Consumption Savings
01 3.1191: Change procedures / equipment / operating conditions $101,400 $60,000 - - - $101,400
-
lb
- -
02 4.652: Replace existing equipment with more suitable substitutes $47,736 $2,000 - - - - $47,736 -
03 4.122: Develop standard procedures to improve internal yields $28,560 $8,000 - - - - $28,560 -
04 2.2511: Insulate bare equipment $19,707 $21,120 - - $19,707
-
MMBtu
- - -
05 2.2136: Install / repair insulation on steam lines $4,026 $1,850 - - $4,026
-
MMBtu
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,699 $6,419 $1,242
32,239
kWh
$457
-
kW-mo/yr
- - - -
07 2.2514: Cover open tanks $2,023 $1,050 - - $686
-
MMBtu
- - $1,337
-
Tgal
TOTAL RECOMMENDED $205,151 $100,439 $1,242
32,239
kWh
$457
-
kW-mo/yr
$24,419
-
MMBtu
$101,400
-
lb
$76,296 $1,337
-
Tgal
TOTAL IMPLEMENTED $34,609 $10,900 - - $4,712
-
MMBtu
- $28,560 $1,337
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs