ITAC Assessment: UD0551
ITAC logo
ITAC Assessment: UD0551
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Rattan and wicker furniture
NAICS
n/a
SIC 2519: Household Furniture, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 35
Plant Area 50,000
ft2
Annual Production 12,500
pieces
Production Hrs. Annual 3,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,041 407,679
kWh
Electricity Demand $21,362 1,764
kW-mo/yr
Natural Gas $24,741 4,096
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,380 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,980

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 4.423: Move product using mechanical means $42,000 $2,400 - - - $42,000
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,897 $10,073 $3,101
97,011
kWh
$4,696
-
kW-mo/yr
- $100
03 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,400 $7,000 - - $2,400
-
lb
-
04 4.652: Replace existing equipment with more suitable substitutes $1,083 $225 - - - $1,083
TOTAL RECOMMENDED $53,380 $19,698 $3,101
97,011
kWh
$4,696
-
kW-mo/yr
$2,400
-
lb
$43,183
TOTAL IMPLEMENTED $8,980 $10,298 $3,101
97,011
kWh
$4,696
-
kW-mo/yr
- $1,183
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs