| Assessment Year | 1997 |
|---|---|
| Principal Product | Steel fabrication |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $5 M to 10M |
| # of Employees | 38 |
| Plant Area |
41,800
ft2
|
| Annual Production | 0
pieces
|
| Production Hrs. Annual | 3,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $27,910 | 664,713 |
kWh
|
$0.042 |
| Electricity Demand | $11,127 | 3,108 |
kW-mo/yr
|
$3.58 |
| Natural Gas | $29,356 | 5,023 |
MMBtu
|
$5.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,696 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,145 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.211: Consider use / purchase of bulk materials where possible | $4,259 | - | - | - | $4,259 | |
| 02 | 2.8112: Combine utility meters | $1,939 | $3,357 |
$1,081
25,791
kWh
|
$386
-
kW-mo/yr
|
$472 | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $92 | - |
$39
879
kWh
|
$53
-
kW-mo/yr
|
- | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $551 | $500 |
$551
13,189
kWh
|
- | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $459 | $1,290 |
$326
7,620
kWh
|
$133
-
kW-mo/yr
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,396 | $200 |
$1,396
33,118
kWh
|
- | - | |
| TOTAL RECOMMENDED | $8,696 | $5,347 |
$3,393
80,597
kWh
|
$572
-
kW-mo/yr
|
$4,731 | ||
| TOTAL IMPLEMENTED | $8,145 | $4,057 |
$3,028
72,098
kWh
|
$386
-
kW-mo/yr
|
$4,731 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs