ITAC Assessment: UD0529
ITAC logo
ITAC Assessment: UD0529
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Steel fabrication
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $5
M
to 10
M
# of Employees 38
Plant Area 41,800
ft2
Annual Production 0
pieces
Production Hrs. Annual 3,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,910 664,713
kWh
Electricity Demand $11,127 3,108
kW-mo/yr
Natural Gas $29,356 5,023
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,696 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,145

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 4.211: Consider use / purchase of bulk materials where possible $4,259 - - - $4,259
02 2.8112: Combine utility meters $1,939 $3,357 $1,081
25,791
kWh
$386
-
kW-mo/yr
$472
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $92 - $39
879
kWh
$53
-
kW-mo/yr
-
04 2.4239: Eliminate or reduce compressed air usage $551 $500 $551
13,189
kWh
- -
05 2.4133: Use most efficient type of electric motors $459 $1,290 $326
7,620
kWh
$133
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,396 $200 $1,396
33,118
kWh
- -
TOTAL RECOMMENDED $8,696 $5,347 $3,393
80,597
kWh
$572
-
kW-mo/yr
$4,731
TOTAL IMPLEMENTED $8,145 $4,057 $3,028
72,098
kWh
$386
-
kW-mo/yr
$4,731
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs