Assessment Year | 1997 |
---|---|
Principal Product | Steel fabrication |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $5 M to 10M |
# of Employees | 38 |
Plant Area |
41,800
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 3,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,910 | 664,713 |
kWh
|
$0.042 |
Electricity Demand | $11,127 | 3,108 |
kW-mo/yr
|
$3.58 |
Natural Gas | $29,356 | 5,023 |
MMBtu
|
$5.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,696 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,145 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 4.211: Consider use / purchase of bulk materials where possible | $4,259 | - | - | - | $4,259 | |
02 | 2.8112: Combine utility meters | $1,939 | $3,357 |
$1,081
25,791
kWh
|
$386
-
kW-mo/yr
|
$472 | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $92 | - |
$39
879
kWh
|
$53
-
kW-mo/yr
|
- | |
04 | 2.4239: Eliminate or reduce compressed air usage | $551 | $500 |
$551
13,189
kWh
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $459 | $1,290 |
$326
7,620
kWh
|
$133
-
kW-mo/yr
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,396 | $200 |
$1,396
33,118
kWh
|
- | - | |
TOTAL RECOMMENDED | $8,696 | $5,347 |
$3,393
80,597
kWh
|
$572
-
kW-mo/yr
|
$4,731 | ||
TOTAL IMPLEMENTED | $8,145 | $4,057 |
$3,028
72,098
kWh
|
$386
-
kW-mo/yr
|
$4,731 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs