ITAC Assessment: UD0528
ITAC logo
ITAC Assessment: UD0528
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product adhesives, resins
NAICS
n/a
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 45
Plant Area 57,000
ft2
Annual Production 0
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,565 464,537
kWh
Electricity Demand $8,268 2,088
kW-mo/yr
Natural Gas $68,181 13,227
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,786 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,927

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings Water Consumption Savings
01 2.1231: Establish burner maintenance schedule for boilers $4,108 - - - $4,108
-
MMBtu
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,857 $10,000 $1,974
29,894
kWh
$571
-
kW-mo/yr
- - $312 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,076 $5,818 $1,818
27,550
kWh
$524
-
kW-mo/yr
- - $734 -
04 3.4116: Meter recycled water (to reduce sewer charges) $2,886 $200 - - - $2,886
-
Tgal
- -
05 3.4111: Use closed cycle process to minimize waste water production $2,859 $11,000 - - - - - $2,859
-
Tgal
TOTAL RECOMMENDED $15,786 $27,018 $3,792
57,444
kWh
$1,095
-
kW-mo/yr
$4,108
-
MMBtu
$2,886
-
Tgal
$1,046 $2,859
-
Tgal
TOTAL IMPLEMENTED $12,927 $16,018 $3,792
57,444
kWh
$1,095
-
kW-mo/yr
$4,108
-
MMBtu
$2,886
-
Tgal
$1,046 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs