Assessment Year | 1997 |
---|---|
Principal Product | adhesives, resins |
NAICS |
n/a
|
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
57,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,565 | 464,537 |
kWh
|
$0.066 |
Electricity Demand | $8,268 | 2,088 |
kW-mo/yr
|
$3.96 |
Natural Gas | $68,181 | 13,227 |
MMBtu
|
$5.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,786 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,927 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1231: Establish burner maintenance schedule for boilers | $4,108 | - | - | - |
$4,108
-
MMBtu
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,857 | $10,000 |
$1,974
29,894
kWh
|
$571
-
kW-mo/yr
|
- | - | $312 | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,076 | $5,818 |
$1,818
27,550
kWh
|
$524
-
kW-mo/yr
|
- | - | $734 | - | |
04 | 3.4116: Meter recycled water (to reduce sewer charges) | $2,886 | $200 | - | - | - |
$2,886
-
Tgal
|
- | - | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $2,859 | $11,000 | - | - | - | - | - |
$2,859
-
Tgal
|
|
TOTAL RECOMMENDED | $15,786 | $27,018 |
$3,792
57,444
kWh
|
$1,095
-
kW-mo/yr
|
$4,108
-
MMBtu
|
$2,886
-
Tgal
|
$1,046 |
$2,859
-
Tgal
|
||
TOTAL IMPLEMENTED | $12,927 | $16,018 |
$3,792
57,444
kWh
|
$1,095
-
kW-mo/yr
|
$4,108
-
MMBtu
|
$2,886
-
Tgal
|
$1,046 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs