Assessment Year | 1997 |
---|---|
Principal Product | organic chemicals |
NAICS |
n/a
|
SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 200 |
Plant Area |
200,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $969,867 | 21,411,489 |
kWh
|
$0.045 |
Electricity Demand | $383,939 | 34,704 |
kW-mo/yr
|
$11.06 |
Natural Gas | $590,298 | 158,619 |
MMBtu
|
$3.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $508,655 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $38,120 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|
01 | 3.4115: Recover and reuse cooling water | $82,051 | $370,000 |
$(-523.0)
(-25,205)
kWh
|
$(-503.0)
-
kW-mo/yr
|
$83,077
-
Tgal
|
|
02 | 3.4115: Recover and reuse cooling water | $82,538 | $50,000 |
$(-277.0)
(-13,189)
kWh
|
$(-262.0)
-
kW-mo/yr
|
$83,077
-
Tgal
|
|
03 | 3.4154: Eliminate leaks in water lines and valves | $195,658 | $50,000 | - | - |
$195,658
-
Tgal
|
|
04 | 2.3212: Optimize plant power factor | $21,006 | $25,000 | - |
$21,006
-
kW-mo/yr
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $3,283 | $6,465 |
$1,259
60,082
kWh
|
$2,024
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,603 | $19,910 |
$4,307
205,158
kWh
|
$6,296
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,228 | $16,000 |
$1,659
79,132
kWh
|
$1,569
-
kW-mo/yr
|
- | |
08 | 3.4116: Meter recycled water (to reduce sewer charges) | $110,288 | $500 | - | - |
$110,288
-
Tgal
|
|
TOTAL RECOMMENDED | $508,655 | $537,875 |
$6,425
305,978
kWh
|
$30,130
-
kW-mo/yr
|
$472,100
-
Tgal
|
||
TOTAL IMPLEMENTED | $38,120 | $67,375 |
$7,225
344,372
kWh
|
$30,895
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs