| Assessment Year | 1997 |
|---|---|
| Principal Product | machinery |
| NAICS |
n/a
|
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
97,000
ft2
|
| Annual Production | 0
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $78,132 | 3,801,876 |
kWh
|
$0.021 |
| Electricity Demand | $122,038 | 7,788 |
kW-mo/yr
|
$15.67 |
| Natural Gas | $38,394 | 7,774 |
MMBtu
|
$4.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $192,844 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.2161: Closely monitor chemical additions to increase bath life | $123,592 | $180,000 | - | - |
$21,120
-
gal
|
$75,000 | $27,472 | |
| 02 | 4.131: Modify process to reduce material use/cost | $30,443 | $20,000 | - | - |
$11,340
-
gal
|
$960 | $18,143 | |
| 03 | 2.3137: Use power during off-peak periods | $24,132 | - | - |
$24,132
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7226: Use computer programs to optimize hvac performance | $7,710 | $5,000 | - |
$7,710
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,882 | $12,861 |
$2,189
104,338
kWh
|
$3,693
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,085 | $2,465 |
$390
18,464
kWh
|
$695
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $192,844 | $220,326 |
$2,579
122,802
kWh
|
$36,230
-
kW-mo/yr
|
$32,460
-
gal
|
$75,960 | $45,615 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs