ITAC Assessment: UD0511
ITAC logo
ITAC Assessment: UD0511
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product aluminum castings
NAICS
n/a
SIC 3365: Aluminum Foundries
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 87,000
ft2
Annual Production 9,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,357 10,496,190
kWh
Electricity Demand $453,842 32,256
kW-mo/yr
Electricity Fees $1,080 -
Natural Gas $270,320 69,282
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $699,487 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $181,054

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,757 $21,000 $1,874
89,390
kWh
$2,511
-
kW-mo/yr
- $1,372 - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $885 $4,700 $378
21,102
kWh
$507
-
kW-mo/yr
- - - -
03 4.513: Re-arrange equipment layout to reduce labor costs $28,000 $12,000 - - - $28,000 - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $27,452 $20,000 $10,626
505,862
kWh
$13,693
-
kW-mo/yr
- - $3,133 -
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $52,379 $35,000 $31,084
1,480,363
kWh
$50,483
-
kW-mo/yr
$(-29,188.0)
-
MMBtu
- - -
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $56,779 $70,000 $31,773
1,053,927
kWh
$30,773
-
kW-mo/yr
$(-5,767.0)
-
MMBtu
- - -
07 2.3191: Use demand controller or load shedder $23,300 - - $23,300
-
kW-mo/yr
- - - -
08 2.1135: Repair furnaces and oven doors so that they seal efficiently $9,802 - $3,644
173,505
kWh
- $6,158
-
MMBtu
- - -
09 2.3212: Optimize plant power factor $6,180 $5,000 - $6,180
-
kW-mo/yr
- - - -
10 3.5221: Recycle casting sand $488,953 $900,000 - - - - - $488,953
TOTAL RECOMMENDED $699,487 $1,067,700 $79,379
3,324,149
kWh
$127,447
-
kW-mo/yr
$(-28,797.0)
-
MMBtu
$29,372 $3,133 $488,953
TOTAL IMPLEMENTED $181,054 $162,700 $79,379
3,324,149
kWh
$97,967
-
kW-mo/yr
$(-28,797.0)
-
MMBtu
$29,372 $3,133 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs