Assessment Year | 1996 |
---|---|
Principal Product | Fabricated structural steel, industrial welding |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
34,000
ft2
|
Annual Production | 3,800
ton
|
Production Hrs. Annual | 2,900
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $11,834 | 374,560 |
kWh
|
$0.032 |
Electricity Demand | $25,576 | 2,112 |
kW-mo/yr
|
$12.11 |
LPG | $16,352 | 1,980 |
MMBtu
|
$8.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,156 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,228 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $5,738 | $7,500 | - | - | - |
$(-8,702.0)
-
MMBtu
|
$14,440
-
MMBtu
|
|
02 | 2.3137: Use power during off-peak periods | $9,357 | - | - |
$10,317
-
kW-mo/yr
|
$(-960.0) | - | - | |
03 | 2.2212: Use minimum safe oven ventilation | $1,228 | $5,000 | - | - | - | - |
$1,228
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $833 | $3,271 |
$386
12,309
kWh
|
$563
-
kW-mo/yr
|
- |
$(-116.0)
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $17,156 | $15,771 |
$386
12,309
kWh
|
$10,880
-
kW-mo/yr
|
$(-960.0) |
$(-8,818.0)
-
MMBtu
|
$15,668
-
MMBtu
|
||
TOTAL IMPLEMENTED | $1,228 | $5,000 | - | - | - | - |
$1,228
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs