Assessment Year | 1996 |
---|---|
Principal Product | felt for shingles |
NAICS |
n/a
|
SIC | 2621: Paper Mills |
Sales Range | $5 M to 10M |
# of Employees | 54 |
Plant Area |
n/a
|
Annual Production | 40,000
ton
|
Production Hrs. Annual | 8,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $505,519 | 17,718,640 |
kWh
|
$0.029 |
Electricity Demand | $317,661 | 32,088 |
kW-mo/yr
|
$9.90 |
Natural Gas | $1,000,529 | 400,212 |
MMBtu
|
$2.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $117,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $117,709 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $25,819 | $30,000 | - |
$25,819
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,461 | $3,112 |
$1,705
81,184
kWh
|
$1,477
-
kW-mo/yr
|
- | - | - | $3,279 | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,228 | $3,710 |
$525
24,912
kWh
|
$455
-
kW-mo/yr
|
- | - | - | $248 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,011 | $1,380 |
$671
31,946
kWh
|
$135
-
kW-mo/yr
|
- | - | - | $205 | - | |
05 | 3.4151: Minimize water usage | $14,124 | - | - | - | - |
$10,660
-
Tgal
|
- | - |
$3,464
-
Tgal
|
|
06 | 3.4154: Eliminate leaks in water lines and valves | $4,054 | $200 | - | - | - |
$3,060
-
Tgal
|
- | - |
$994
-
Tgal
|
|
07 | 3.4155: Meter waste water | $30,899 | $1,000 | - | - | - |
$23,320
-
Tgal
|
- | - |
$7,579
-
Tgal
|
|
08 | 2.2163: Use minimum steam operating pressure | $4,188 | - | - | - |
$4,188
-
MMBtu
|
- | - | - | - | |
09 | 2.2511: Insulate bare equipment | $628 | $2,040 | - | - |
$628
-
MMBtu
|
- | - | - | - | |
10 | 4.321: Optimize production lot sizes and inventories | $29,297 | - |
$1,665
79,132
kWh
|
$3,894
-
kW-mo/yr
|
- | - | $23,738 | - | - | |
TOTAL RECOMMENDED | $117,709 | $41,442 |
$4,566
217,174
kWh
|
$31,780
-
kW-mo/yr
|
$4,816
-
MMBtu
|
$37,040
-
Tgal
|
$23,738 | $3,732 |
$12,037
-
Tgal
|
||
TOTAL IMPLEMENTED | $117,709 | $41,442 |
$4,566
217,174
kWh
|
$31,780
-
kW-mo/yr
|
$4,816
-
MMBtu
|
$37,040
-
Tgal
|
$23,738 | $3,732 |
$12,037
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs