Assessment Year | 1996 |
---|---|
Principal Product | bronzed baby shoes |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
40,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,100
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $46,917 | 691,383 |
kWh
|
$0.068 |
Electricity Demand | $13,361 | 3,516 |
kW-mo/yr
|
$3.80 |
Natural Gas | $33,781 | 6,979 |
MMBtu
|
$4.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,153 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $866 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4113: Treat and reuse rinse waters | $6,700 | $2,000 |
$(-109.0)
(-1,758)
kWh
|
$(-36.0)
-
kW-mo/yr
|
- |
$6,845
-
Tgal
|
- | - | - | |
02 | 3.1161: Eliminate/reduce an operation | $2,200 | $600 | - | - | - | - |
$1,600
-
gal
|
$600
-
lb
|
- | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $866 | - | - |
$866
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $656 | $700 |
$347
5,275
kWh
|
$116
-
kW-mo/yr
|
$(-63.0)
-
MMBtu
|
- | - | - | $256 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,731 | $6,298 |
$384
18,171
kWh
|
$1,347
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $12,153 | $9,598 |
$622
21,688
kWh
|
$2,293
-
kW-mo/yr
|
$(-63.0)
-
MMBtu
|
$6,845
-
Tgal
|
$1,600
-
gal
|
$600
-
lb
|
$256 | ||
TOTAL IMPLEMENTED | $866 | - | - |
$866
-
kW-mo/yr
|
- | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs