ITAC Assessment: UD0498
ITAC logo
ITAC Assessment: UD0498
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product bronzed baby shoes
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area 40,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,100
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,917 691,383
kWh
Electricity Demand $13,361 3,516
kW-mo/yr
Natural Gas $33,781 6,979
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,153 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $866

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 3.4113: Treat and reuse rinse waters $6,700 $2,000 $(-109.0)
(-1,758)
kWh
$(-36.0)
-
kW-mo/yr
- $6,845
-
Tgal
- - -
02 3.1161: Eliminate/reduce an operation $2,200 $600 - - - - $1,600
-
gal
$600
-
lb
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $866 - - $866
-
kW-mo/yr
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $656 $700 $347
5,275
kWh
$116
-
kW-mo/yr
$(-63.0)
-
MMBtu
- - - $256
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,731 $6,298 $384
18,171
kWh
$1,347
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $12,153 $9,598 $622
21,688
kWh
$2,293
-
kW-mo/yr
$(-63.0)
-
MMBtu
$6,845
-
Tgal
$1,600
-
gal
$600
-
lb
$256
TOTAL IMPLEMENTED $866 - - $866
-
kW-mo/yr
- - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs