| Assessment Year | 1996 |
|---|---|
| Principal Product | corrugated boxes |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 64 |
| Plant Area |
130,800
ft2
|
| Annual Production | 25,000
lb
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $90,911 | 3,738,570 |
kWh
|
$0.024 |
| Electricity Demand | $125,847 | 10,392 |
kW-mo/yr
|
$12.11 |
| Natural Gas | $104,062 | 35,073 |
MMBtu
|
$2.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,165 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,405 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,040 | $1,500 | - | - |
$2,040
-
MMBtu
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,270 | $5,000 |
$1,680
80,012
kWh
|
$3,760
-
kW-mo/yr
|
$(-1,170.0)
-
MMBtu
|
- | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $17,005 | $30,000 |
$6,615
315,064
kWh
|
$15,790
-
kW-mo/yr
|
$(-5,400.0)
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $365 | $1,720 |
$116
5,569
kWh
|
$231
-
kW-mo/yr
|
- | $18 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,485 | $18,550 |
$2,429
115,768
kWh
|
$4,832
-
kW-mo/yr
|
$(-776.0)
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $30,165 | $56,770 |
$10,840
516,413
kWh
|
$24,613
-
kW-mo/yr
|
$(-5,306.0)
-
MMBtu
|
$18 | ||
| TOTAL IMPLEMENTED | $2,405 | $3,220 |
$116
5,569
kWh
|
$231
-
kW-mo/yr
|
$2,040
-
MMBtu
|
$18 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs