| Assessment Year | 1996 |
|---|---|
| Principal Product | Large Aluminum casted components |
| NAICS |
n/a
|
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
97,000
ft2
|
| Annual Production | 500
ton
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $50,210 | 1,569,461 |
kWh
|
$0.032 |
| Electricity Demand | $70,190 | 5,796 |
kW-mo/yr
|
$12.11 |
| Natural Gas | $12,466 | 5,303 |
MMBtu
|
$2.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $61,774 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $1,502 | $4,000 | - |
$1,502
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.3191: Use demand controller or load shedder | $13,369 | $500 | - |
$13,369
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $33,600 | - | - |
$32,400
-
kW-mo/yr
|
$1,200 | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $956 | $3,035 |
$425
13,189
kWh
|
$531
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,168 | $3,450 |
$1,015
32,825
kWh
|
$1,003
-
kW-mo/yr
|
- | - | $150 | |
| 06 | 3.5221: Recycle casting sand | $10,179 | $15,000 |
$(-128.0)
(-4,103)
kWh
|
$(-1,453.0)
-
kW-mo/yr
|
- |
$11,760
-
lb
|
- | |
| TOTAL RECOMMENDED | $61,774 | $25,985 |
$1,312
41,911
kWh
|
$47,352
-
kW-mo/yr
|
$1,200 |
$11,760
-
lb
|
$150 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs