ITAC Assessment: UD0487
ITAC logo
ITAC Assessment: UD0487
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Large Aluminum casted components
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 97,000
ft2
Annual Production 500
ton
Production Hrs. Annual 5,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,210 1,569,461
kWh
Electricity Demand $70,190 5,796
kW-mo/yr
Natural Gas $12,466 5,303
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,774 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.3212: Optimize plant power factor $1,502 $4,000 - $1,502
-
kW-mo/yr
- - -
02 2.3191: Use demand controller or load shedder $13,369 $500 - $13,369
-
kW-mo/yr
- - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $33,600 - - $32,400
-
kW-mo/yr
$1,200 - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $956 $3,035 $425
13,189
kWh
$531
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,168 $3,450 $1,015
32,825
kWh
$1,003
-
kW-mo/yr
- - $150
06 3.5221: Recycle casting sand $10,179 $15,000 $(-128.0)
(-4,103)
kWh
$(-1,453.0)
-
kW-mo/yr
- $11,760
-
lb
-
TOTAL RECOMMENDED $61,774 $25,985 $1,312
41,911
kWh
$47,352
-
kW-mo/yr
$1,200 $11,760
-
lb
$150
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs