ITAC Assessment: UD0479
ITAC logo
ITAC Assessment: UD0479
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product specialized military equipment
NAICS
n/a
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $10
M
to 50
M
# of Employees 270
Plant Area 171,000
ft2
Annual Production 0
units
Production Hrs. Annual 7,200
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $258,756 4,381,301
kWh
Natural Gas $44,036 8,111
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,046 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,046

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 3.4116: Meter recycled water (to reduce sewer charges) $1,667 - - - $1,667
-
Tgal
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $12,043 $16,000 $11,997
184,056
kWh
$(-4,914.0)
-
MMBtu
- $4,960
03 2.7142: Utilize higher efficiency lamps and/or ballasts $8,152 $17,500 $8,274
149,179
kWh
$(-982.0)
-
MMBtu
- $860
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,184 $14,654 $8,519
118,406
kWh
$(-1,335.0)
-
MMBtu
- -
TOTAL RECOMMENDED $29,046 $48,154 $28,790
451,641
kWh
$(-7,231.0)
-
MMBtu
$1,667
-
Tgal
$5,820
TOTAL IMPLEMENTED $29,046 $48,154 $28,790
451,641
kWh
$(-7,231.0)
-
MMBtu
$1,667
-
Tgal
$5,820
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs