| Assessment Year | 1995 |
|---|---|
| Principal Product | specialized military equipment |
| NAICS |
n/a
|
| SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 270 |
| Plant Area |
171,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $258,756 | 4,381,301 |
kWh
|
$0.059 |
| Natural Gas | $44,036 | 8,111 |
MMBtu
|
$5.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,046 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,046 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,667 | - | - | - |
$1,667
-
Tgal
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $12,043 | $16,000 |
$11,997
184,056
kWh
|
$(-4,914.0)
-
MMBtu
|
- | $4,960 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,152 | $17,500 |
$8,274
149,179
kWh
|
$(-982.0)
-
MMBtu
|
- | $860 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,184 | $14,654 |
$8,519
118,406
kWh
|
$(-1,335.0)
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $29,046 | $48,154 |
$28,790
451,641
kWh
|
$(-7,231.0)
-
MMBtu
|
$1,667
-
Tgal
|
$5,820 | ||
| TOTAL IMPLEMENTED | $29,046 | $48,154 |
$28,790
451,641
kWh
|
$(-7,231.0)
-
MMBtu
|
$1,667
-
Tgal
|
$5,820 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs