| Assessment Year | 1995 |
|---|---|
| Principal Product | corrugated shipping containers |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 91 |
| Plant Area |
140,000
ft2
|
| Annual Production | 40,000
ton
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $220,577 | 3,669,695 |
kWh
|
$0.060 |
| Natural Gas | $150,000 | 47,865 |
MMBtu
|
$3.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,863 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $40,004 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $1,927 | - | - |
$1,927
-
MMBtu
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $6,045 | $4,000 | - |
$6,045
-
MMBtu
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,867 | $5,759 |
$2,867
34,291
kWh
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,444 | $4,300 |
$3,129
63,892
kWh
|
- | - | $315 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,196 | $21,000 |
$3,969
81,184
kWh
|
$(-613.0)
-
MMBtu
|
- | $2,840 | |
| 06 | 3.4116: Meter recycled water (to reduce sewer charges) | $3,150 | $250 | - | - | - | $3,150 | |
| 07 | 3.4156: Use flow control valves on equipment to optimize water use | $1,625 | $600 | - | - |
$1,625
-
Tgal
|
- | |
| 08 | 3.4115: Recover and reuse cooling water | $10,234 | $2,500 | - |
$484
-
MMBtu
|
$9,750
-
Tgal
|
- | |
| 09 | 3.4115: Recover and reuse cooling water | $16,375 | $7,500 | - |
$775
-
MMBtu
|
$15,600
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $51,863 | $45,909 |
$9,965
179,367
kWh
|
$8,618
-
MMBtu
|
$26,975
-
Tgal
|
$6,305 | ||
| TOTAL IMPLEMENTED | $40,004 | $42,809 |
$9,965
179,367
kWh
|
$8,134
-
MMBtu
|
$15,600
-
Tgal
|
$6,305 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs