ITAC Assessment: UD0459
ITAC logo
ITAC Assessment: UD0459
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product rag and cotton linter pulp
NAICS
n/a
SIC 2823: Cellulosic Manmade Fibers
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 50,000
ft2
Annual Production 10,000
ton
Production Hrs. Annual 8,400
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $543,836 10,823,271
kWh
Natural Gas $126,112 36,032
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $607,146 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $605,972

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $9,255 $3,200 $9,255
-
kWh
- - - -
02 3.5313: Increase amount of waste recovered for resale $9,913 $1,000 $(-337.0)
(-8,499)
kWh
- - $11,250
-
lb
$(-1,000.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,174 $2,605 $1,174
29,308
kWh
- - - -
04 3.1191: Change procedures / equipment / operating conditions $41,743 $340,000 $3,370
84,115
kWh
- $59,150
-
Tgal
$(-20,777.0)
-
lb
-
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $545,061 $4,500,000 - $(-70,589.0)
-
MMBtu
$620,650
-
Tgal
- $(-5,000.0)
TOTAL RECOMMENDED $607,146 $4,846,805 $13,462
104,924
kWh
$(-70,589.0)
-
MMBtu
$679,800
-
Tgal
$(-9,527.0)
-
lb
$(-6,000.0)
TOTAL IMPLEMENTED $605,972 $4,844,200 $12,288
75,616
kWh
$(-70,589.0)
-
MMBtu
$679,800
-
Tgal
$(-9,527.0)
-
lb
$(-6,000.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs