Assessment Year | 1995 |
---|---|
Principal Product | rag and cotton linter pulp |
NAICS |
n/a
|
SIC | 2823: Cellulosic Manmade Fibers |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
50,000
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $543,836 | 10,823,271 |
kWh
|
$0.050 |
Natural Gas | $126,112 | 36,032 |
MMBtu
|
$3.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $607,146 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $605,972 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $9,255 | $3,200 |
$9,255
-
kWh
|
- | - | - | - | |
02 | 3.5313: Increase amount of waste recovered for resale | $9,913 | $1,000 |
$(-337.0)
(-8,499)
kWh
|
- | - |
$11,250
-
lb
|
$(-1,000.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,174 | $2,605 |
$1,174
29,308
kWh
|
- | - | - | - | |
04 | 3.1191: Change procedures / equipment / operating conditions | $41,743 | $340,000 |
$3,370
84,115
kWh
|
- |
$59,150
-
Tgal
|
$(-20,777.0)
-
lb
|
- | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $545,061 | $4,500,000 | - |
$(-70,589.0)
-
MMBtu
|
$620,650
-
Tgal
|
- | $(-5,000.0) | |
TOTAL RECOMMENDED | $607,146 | $4,846,805 |
$13,462
104,924
kWh
|
$(-70,589.0)
-
MMBtu
|
$679,800
-
Tgal
|
$(-9,527.0)
-
lb
|
$(-6,000.0) | ||
TOTAL IMPLEMENTED | $605,972 | $4,844,200 |
$12,288
75,616
kWh
|
$(-70,589.0)
-
MMBtu
|
$679,800
-
Tgal
|
$(-9,527.0)
-
lb
|
$(-6,000.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs