| Assessment Year | 1994 |
|---|---|
| Principal Product | reconditioned steel drums |
| NAICS |
n/a
|
| SIC | 3412: Metal Shipping Barrels, Drums, Kegs, and Pails |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
35,000
ft2
|
| Annual Production | 370,000
pieces
|
| Production Hrs. Annual | 4,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $124,010 | 1,640,973 |
kWh
|
$0.076 |
| Natural Gas | $121,805 | 47,725 |
MMBtu
|
$2.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $104,000 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $101,575 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Energy Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $5,693 | $10,000 |
$5,693
172,040
kWh
|
- | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $2,425 | $5,000 | - |
$2,425
-
MMBtu
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,410 | $2,106 |
$2,410
72,685
kWh
|
- | - | - | - | |
| 04 | 2.2444: Use hot process fluids to preheat incoming process fluids | $268 | $500 | - | - | - |
$268
-
MMBtu
|
- | |
| 05 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $2,919 | $5,000 | - |
$2,919
-
MMBtu
|
- | - | - | |
| 06 | 2.8112: Combine utility meters | $89,640 | $40,000 | - |
$1,680
-
MMBtu
|
$(-3,000.0)
-
MMBtu
|
- | $90,960 | |
| 07 | 2.2136: Install / repair insulation on steam lines | $645 | $500 | - |
$645
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $104,000 | $63,106 |
$8,103
244,725
kWh
|
$7,669
-
MMBtu
|
$(-3,000.0)
-
MMBtu
|
$268
-
MMBtu
|
$90,960 | ||
| TOTAL IMPLEMENTED | $101,575 | $58,106 |
$8,103
244,725
kWh
|
$5,244
-
MMBtu
|
$(-3,000.0)
-
MMBtu
|
$268
-
MMBtu
|
$90,960 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Other Energy Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs