ITAC Assessment: UD0429
ITAC logo
ITAC Assessment: UD0429
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product metal cabinets
NAICS
n/a
SIC 2522: Office Furniture, Except Wood
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 53,800
ft2
Annual Production 6,000
pieces
Production Hrs. Annual 3,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,814 168,816
kWh
Natural Gas $9,853 1,950
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,792 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $834

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Coal Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $585 $1,250 $417
4,982
kWh
- - $168
02 2.7142: Utilize higher efficiency lamps and/or ballasts $249 $44 $225
2,931
kWh
- - $24
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $260 $500 $428
6,448
kWh
$(-168.0)
-
MMBtu
- -
04 2.1332: Convert combustion equipment to burn natural gas $3,500 $50,000 - - $3,000
-
MMBtu
$500
05 2.4133: Use most efficient type of electric motors $198 $240 $198
2,345
kWh
- - -
TOTAL RECOMMENDED $4,792 $52,034 $1,268
16,706
kWh
$(-168.0)
-
MMBtu
$3,000
-
MMBtu
$692
TOTAL IMPLEMENTED $834 $1,294 $642
7,913
kWh
- - $192
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs