Assessment Year | 2006 |
---|---|
Principal Product | Plywood Manufacturing |
NAICS | 321212: Softwood Veneer and Plywood Manufacturing |
SIC | 2436: Softwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 315 |
Plant Area |
200,000
ft2
|
Annual Production | 315,000
thousand feet
|
Production Hrs. Annual | 6,656
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,594,488 | 42,714,647 |
kWh
|
$0.061 |
Electricity Demand | $48,525 | 6,602 |
kW-mo/yr
|
$7.35 |
Natural Gas | $1,285,760 | 176,287 |
MMBtu
|
$7.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $497,284 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $434,072 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $178,198 | $64,440 |
$171,674
2,826,368
kWh
|
- | $6,524 | - | - | - | |
02 | 2.2135: Repair and eliminate steam leaks | $149,914 | $3,400 | - | - | - | - |
$149,914
-
MMBtu
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $77,103 | $3,196 |
$74,280
1,222,919
kWh
|
- | $2,823 | - | - | - | |
04 | 2.2441: Preheat boiler makeup water with waste process heat | $55,105 | $40,000 | - | - | - | - |
$55,105
-
MMBtu
|
- | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $20,822 | $1,320 |
$17,142
282,244
kWh
|
$2,918
-
kW-mo/yr
|
$762 | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,436 | $30 |
$5,237
86,216
kWh
|
- | $199 | - | - | - | |
07 | 2.7134: Use photocell controls | $3,211 | $600 |
$3,093
50,917
kWh
|
- | $118 | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,567 | $1,700 |
$1,011
16,644
kWh
|
- | $38 | - | - | $1,518 | |
09 | 4.611: Begin a practice of predictive / preventative maintenance | $1,743 | $2,445 | - | - | - | - | - | $1,743 | |
10 | 2.2511: Insulate bare equipment | $1,977 | $2,653 | - | - | - |
$1,619
-
MMBtu
|
$358
-
MMBtu
|
- | |
11 | 2.7224: Reduce space conditioning during non-working hours | $715 | $1,400 |
$689
11,344
kWh
|
- | $26 | - | - | - | |
12 | 2.7135: Install occupancy sensors | $213 | $270 |
$205
3,370
kWh
|
- | $8 | - | - | - | |
13 | 2.2511: Insulate bare equipment | $280 | $409 | - | - | - | - |
$280
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $497,284 | $121,863 |
$273,331
4,500,022
kWh
|
$2,918
-
kW-mo/yr
|
$10,498 |
$1,619
-
MMBtu
|
$205,657
-
MMBtu
|
$3,261 | ||
TOTAL IMPLEMENTED | $434,072 | $77,718 |
$267,200
4,399,092
kWh
|
$2,918
-
kW-mo/yr
|
$10,265 |
$1,619
-
MMBtu
|
$150,552
-
MMBtu
|
$1,518 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs