| Assessment Year | 1994 |
|---|---|
| Principal Product | folding cartons |
| NAICS |
n/a
|
| SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
220,000
ft2
|
| Annual Production | 25,000
ton
|
| Production Hrs. Annual | 6,400
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $399,638 | 8,396,835 |
kWh
|
$0.048 |
| Natural Gas | $58,983 | 12,881 |
MMBtu
|
$4.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $117,234 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $36,954 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $18,774 | $50,000 | - | - | $18,774 | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $62,721 | $150,000 | - | - | $62,721 | |
| 03 | 2.3191: Use demand controller or load shedder | $16,236 | $30,000 |
$16,236
-
kWh
|
- | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $1,024 | $400 |
$1,024
22,860
kWh
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $17,559 | $10,000 |
$(-1,619.0)
(-74,150)
kWh
|
$19,178
-
MMBtu
|
- | |
| 06 | 2.6218: Turn off equipment when not in use | $920 | - |
$502
23,154
kWh
|
$418
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $117,234 | $240,400 |
$16,143
(-28,136)
kWh
|
$19,596
-
MMBtu
|
$81,495 | ||
| TOTAL IMPLEMENTED | $36,954 | $80,400 |
$17,762
46,014
kWh
|
$418
-
MMBtu
|
$18,774 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs