ITAC Assessment: UD0396
ITAC logo
ITAC Assessment: UD0396
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product aircraft flight control hardwar
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 38
Plant Area 21,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,064 286,928
kWh
Natural Gas $4,725 1,261
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $816 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $816

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7111: Reduce illumination to minimum necessary levels $71 $15 $71
2,052
kWh
-
02 2.7111: Reduce illumination to minimum necessary levels $745 $700 $1,098
33,705
kWh
$(-353.0)
-
MMBtu
TOTAL RECOMMENDED $816 $715 $1,169
35,757
kWh
$(-353.0)
-
MMBtu
TOTAL IMPLEMENTED $816 $715 $1,169
35,757
kWh
$(-353.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs