ITAC Assessment: UD0389
ITAC logo
ITAC Assessment: UD0389
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PROCESSED MEAT PRODUCTS
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $10
M
to 50
M
# of Employees 115
Plant Area
n/a
Annual Production 14,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $142,168 2,414,713
kWh
Natural Gas $27,976 6,470
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,987 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,991

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,419 - $2,419
-
kWh
-
02 2.7111: Reduce illumination to minimum necessary levels $643 $50 $720
9,379
kWh
$(-77.0)
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,929 $6,000 $2,929
43,376
kWh
-
04 2.8114: Change rate schedules or other changes in utility service $12,996 $25,000 $12,996
-
kWh
-
TOTAL RECOMMENDED $18,987 $31,050 $19,064
52,755
kWh
$(-77.0)
-
MMBtu
TOTAL IMPLEMENTED $5,991 $6,050 $6,068
52,755
kWh
$(-77.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs