| Assessment Year | 1992 |
|---|---|
| Principal Product | STEEL DOORS |
| NAICS |
n/a
|
| SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
| Sales Range | $50 M to 100M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 730,000
pieces
|
| Production Hrs. Annual | 8,300
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $257,078 | 4,893,904 |
kWh
|
$0.053 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,254 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $72,363 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3511: Use plant owned transformers or lease transformers | $23,256 | $55,000 |
$23,256
-
kWh
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $35,120 | $38,000 |
$62,874
1,258,793
kWh
|
$(-27,754.0)
-
MMBtu
|
|
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,668 | - |
$5,425
253,517
kWh
|
$(-757.0)
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $1,850 | $1,000 |
$696
32,532
kWh
|
$1,154
-
MMBtu
|
|
| 05 | 2.4322: Use or replace with energy efficient substitutes | $4,875 | $2,000 |
$4,875
94,959
kWh
|
- | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $891 | - |
$891
13,775
kWh
|
- | |
| 07 | 2.7224: Reduce space conditioning during non-working hours | $2,594 | $1,000 | - |
$2,594
-
MMBtu
|
|
| TOTAL RECOMMENDED | $73,254 | $97,000 |
$98,017
1,653,576
kWh
|
$(-24,763.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $72,363 | $97,000 |
$97,126
1,639,801
kWh
|
$(-24,763.0)
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs