ITAC Assessment: UD0387
ITAC logo
ITAC Assessment: UD0387
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product STEEL DOORS
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area
n/a
Annual Production 730,000
pieces
Production Hrs. Annual 8,300
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $257,078 4,893,904
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $73,254 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $72,363

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3511: Use plant owned transformers or lease transformers $23,256 $55,000 $23,256
-
kWh
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $35,120 $38,000 $62,874
1,258,793
kWh
$(-27,754.0)
-
MMBtu
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $4,668 - $5,425
253,517
kWh
$(-757.0)
-
MMBtu
04 2.2437: Recover waste heat from equipment $1,850 $1,000 $696
32,532
kWh
$1,154
-
MMBtu
05 2.4322: Use or replace with energy efficient substitutes $4,875 $2,000 $4,875
94,959
kWh
-
06 2.6212: Turn off equipment during breaks, reduce operating time $891 - $891
13,775
kWh
-
07 2.7224: Reduce space conditioning during non-working hours $2,594 $1,000 - $2,594
-
MMBtu
TOTAL RECOMMENDED $73,254 $97,000 $98,017
1,653,576
kWh
$(-24,763.0)
-
MMBtu
TOTAL IMPLEMENTED $72,363 $97,000 $97,126
1,639,801
kWh
$(-24,763.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs