Assessment Year | 1992 |
---|---|
Principal Product | STEEL DOORS |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 730,000
pieces
|
Production Hrs. Annual | 8,300
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $257,078 | 4,893,904 |
kWh
|
$0.053 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $73,254 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $72,363 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3511: Use plant owned transformers or lease transformers | $23,256 | $55,000 |
$23,256
-
kWh
|
- | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $35,120 | $38,000 |
$62,874
1,258,793
kWh
|
$(-27,754.0)
-
MMBtu
|
|
03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,668 | - |
$5,425
253,517
kWh
|
$(-757.0)
-
MMBtu
|
|
04 | 2.2437: Recover waste heat from equipment | $1,850 | $1,000 |
$696
32,532
kWh
|
$1,154
-
MMBtu
|
|
05 | 2.4322: Use or replace with energy efficient substitutes | $4,875 | $2,000 |
$4,875
94,959
kWh
|
- | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $891 | - |
$891
13,775
kWh
|
- | |
07 | 2.7224: Reduce space conditioning during non-working hours | $2,594 | $1,000 | - |
$2,594
-
MMBtu
|
|
TOTAL RECOMMENDED | $73,254 | $97,000 |
$98,017
1,653,576
kWh
|
$(-24,763.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $72,363 | $97,000 |
$97,126
1,639,801
kWh
|
$(-24,763.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs