ITAC Assessment: UD0383
ITAC logo
ITAC Assessment: UD0383
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product AUTOMOTIVE PLASTIC PARTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 329
Plant Area
n/a
Annual Production 850,000
pieces
Production Hrs. Annual 6,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $512,212 11,082,357
kWh
Natural Gas $35,194 10,347
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,155 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,344

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $1,953 $500 $1,664
74,736
kWh
$289
-
MMBtu
02 2.6242: Minimize operation of equipment maintained in standby condition $8,673 $2,000 $8,673
-
kWh
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $11,174 - $11,174
-
kWh
-
04 2.2437: Recover waste heat from equipment $1,389 $400 - $1,389
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $11,329 $13,345 $11,951
218,054
kWh
$(-622.0)
-
MMBtu
06 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $15,637 $47,000 $4,213
91,149
kWh
$11,424
-
MMBtu
TOTAL RECOMMENDED $50,155 $63,245 $37,675
383,939
kWh
$12,480
-
MMBtu
TOTAL IMPLEMENTED $23,344 $16,245 $22,288
292,790
kWh
$1,056
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs