| Assessment Year | 1995 |
|---|---|
| Principal Product | Titanium castings |
| NAICS |
n/a
|
| SIC | 3369: Nonferrous Foundries, Except Aluminum and Copper |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
52,000
ft2
|
| Annual Production | 293,469
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $221,172 | 5,351,114 |
kWh
|
$0.041 |
| Natural Gas | $54,568 | 12,486 |
MMBtu
|
$4.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $147,881 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $130,881 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2423: Install waste heat boiler to produce steam | $12,000 | $19,000 | - |
$12,000
-
MMBtu
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $2,521 | $6,281 |
$2,521
62,134
kWh
|
- | - | - | |
| 03 | 3.4151: Minimize water usage | $3,070 | - | - | - |
$3,070
-
Tgal
|
- | |
| 04 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $122,760 | $205,000 | - | - | - |
$122,760
-
lb
|
|
| 05 | 3.4114: Replace city water with recycled water via cooling tower | $2,530 | $6,500 | - | - |
$2,530
-
Tgal
|
- | |
| 06 | 2.3212: Optimize plant power factor | $5,000 | $14,000 |
$5,000
-
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $147,881 | $250,781 |
$7,521
62,134
kWh
|
$12,000
-
MMBtu
|
$5,600
-
Tgal
|
$122,760
-
lb
|
||
| TOTAL IMPLEMENTED | $130,881 | $217,781 |
$2,521
62,134
kWh
|
- |
$5,600
-
Tgal
|
$122,760
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs