ITAC Assessment: UD0358
ITAC logo
ITAC Assessment: UD0358
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product PIANO PLATES/FRAMES
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 83
Plant Area
n/a
Annual Production 55,000
pieces
Production Hrs. Annual 5,800
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $463,332 9,428,781
kWh
Natural Gas $57,734 12,344
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,049 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,049

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3191: Use demand controller or load shedder $10,464 $7,000 $10,464
-
kWh
- -
02 2.6121: Reduce hot water temperature to the minimum required $675 - - $675
-
MMBtu
-
03 2.6121: Reduce hot water temperature to the minimum required $2,145 $200 - $2,145
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,170 - $4,314
45,428
kWh
- $856
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,636 - $4,236
71,219
kWh
- $400
06 2.7142: Utilize higher efficiency lamps and/or ballasts $959 - $314
5,275
kWh
- $645
TOTAL RECOMMENDED $24,049 $7,200 $19,328
121,922
kWh
$2,820
-
MMBtu
$1,901
TOTAL IMPLEMENTED $24,049 $7,200 $19,328
121,922
kWh
$2,820
-
MMBtu
$1,901
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs