| Assessment Year | 1991 |
|---|---|
| Principal Product | SHEET METAL FABRICATION |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 43 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,750
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $53,196 | 676,729 |
kWh
|
$0.079 |
| Natural Gas | $27,520 | 6,490 |
MMBtu
|
$4.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,012 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,012 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $741 | $624 |
$741
5,275
kWh
|
- | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,333 | - |
$1,333
-
kWh
|
- | - | |
| 03 | 2.4322: Use or replace with energy efficient substitutes | $3,459 | - |
$1,639
21,981
kWh
|
$420
-
MMBtu
|
$1,400 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,479 | - |
$6,829
91,735
kWh
|
$(-626.0)
-
MMBtu
|
$276 | |
| TOTAL RECOMMENDED | $12,012 | $624 |
$10,542
118,991
kWh
|
$(-206.0)
-
MMBtu
|
$1,676 | ||
| TOTAL IMPLEMENTED | $12,012 | $624 |
$10,542
118,991
kWh
|
$(-206.0)
-
MMBtu
|
$1,676 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs