| Assessment Year | 1990 |
|---|---|
| Principal Product | TRANSMISSION DIE CASTS |
| NAICS |
n/a
|
| SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
n/a
|
| Annual Production | 30
pieces
|
| Production Hrs. Annual | 7,500
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $168,366 | 3,429,074 |
kWh
|
$0.049 |
| Natural Gas | $28,658 | 5,727 |
MMBtu
|
$5.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,667 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,372 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $2,550 | $3,000 |
$2,311
58,910
kWh
|
$239
-
MMBtu
|
- | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,372 | - |
$2,372
-
kWh
|
- | - | |
| 03 | 2.3134: Shift from daytime to nighttime operation | $3,745 | - |
$4,745
-
kWh
|
- | $(-1,000.0) | |
| TOTAL RECOMMENDED | $8,667 | $3,000 |
$9,428
58,910
kWh
|
$239
-
MMBtu
|
$(-1,000.0) | ||
| TOTAL IMPLEMENTED | $2,372 | - |
$2,372
-
kWh
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs