| Assessment Year | 1990 |
|---|---|
| Principal Product | PAPERBOARD CARTONS |
| NAICS |
n/a
|
| SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
| Sales Range | $10 M to 50M |
| # of Employees | 146 |
| Plant Area |
n/a
|
| Annual Production | 42,000
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $312,453 | 6,454,865 |
kWh
|
$0.048 |
| Natural Gas | $187,138 | 50,380 |
MMBtu
|
$3.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $69,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,391 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $8,661 | $5,500 |
$8,661
105,803
kWh
|
- | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $9,752 | $11,000 |
$9,752
242,087
kWh
|
- | - | |
| 03 | 2.7141: Lower light fixtures in high ceiling areas | $1,240 | $300 |
$1,483
33,118
kWh
|
$(-243.0)
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,774 | $27,775 |
$10,536
262,896
kWh
|
$(-1,346.0)
-
MMBtu
|
$584 | |
| 05 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $32,480 | $60,000 | - |
$32,480
-
MMBtu
|
- | |
| 06 | 2.2443: Re-use or recycle hot or cold process exhaust air | $7,978 | $20,000 | - |
$7,978
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $69,885 | $124,575 |
$30,432
643,904
kWh
|
$38,869
-
MMBtu
|
$584 | ||
| TOTAL IMPLEMENTED | $26,391 | $36,500 |
$18,413
347,890
kWh
|
$7,978
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs