| Assessment Year | 1990 |
|---|---|
| Principal Product | REFRIGERATORS,ICE MAKERS |
| NAICS |
n/a
|
| SIC | 3632: Household Refrigerators and HOme and Farm Freezers |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 17,500
pieces
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $70,938 | 1,359,906 |
kWh
|
$0.052 |
| Natural Gas | $19,871 | 3,941 |
MMBtu
|
$5.04 |
| LPG | $8,714 | 1,282 |
MMBtu
|
$6.80 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,566 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,979 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1332: Convert combustion equipment to burn natural gas | $2,239 | - | - |
$(-6,475.0)
-
MMBtu
|
$8,714
-
MMBtu
|
- | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $7,073 | $300 | - |
$7,073
-
MMBtu
|
- | - | |
| 03 | 3.4115: Recover and reuse cooling water | $1,984 | $300 | - | - | - | $1,984 | |
| 04 | 2.2437: Recover waste heat from equipment | $1,470 | $3,000 | - |
$1,470
-
MMBtu
|
- | - | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $11,821 | $23,000 |
$16,861
322,978
kWh
|
$(-5,040.0)
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,979 | $16,000 |
$11,007
210,727
kWh
|
$(-1,028.0)
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $34,566 | $42,600 |
$27,868
533,705
kWh
|
$(-4,000.0)
-
MMBtu
|
$8,714
-
MMBtu
|
$1,984 | ||
| TOTAL IMPLEMENTED | $9,979 | $16,000 |
$11,007
210,727
kWh
|
$(-1,028.0)
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs