| Assessment Year | 1988 |
|---|---|
| Principal Product | METAL STAMPINGS |
| NAICS |
n/a
|
| SIC | 3465: Automotive Stampings |
| Sales Range | $1 M to 5M |
| # of Employees | 90 |
| Plant Area |
n/a
|
| Annual Production | 1,500,000
pieces
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $73,034 | 890,094 |
kWh
|
$0.082 |
| LPG | $18,503 | 2,632 |
MMBtu
|
$7.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,718 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $4,019 | $15,000 |
$4,019
-
kWh
|
- | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,000 | - |
$8,231
-
kWh
|
- | $(-2,231.0) | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,423 | $1,000 |
$7,043
62,720
kWh
|
$(-620.0)
-
MMBtu
|
- | |
| 04 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,534 | - |
$2,880
21,102
kWh
|
$(-346.0)
-
MMBtu
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $1,981 | $1,500 | - |
$1,381
-
MMBtu
|
$600 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,295 | $9,000 |
$8,444
114,596
kWh
|
- | $851 | |
| TOTAL RECOMMENDED | $30,252 | $26,500 |
$30,617
198,418
kWh
|
$415
-
MMBtu
|
$(-780.0) | ||
| TOTAL IMPLEMENTED | $21,718 | $26,500 |
$19,506
177,316
kWh
|
$761
-
MMBtu
|
$1,451 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs