ITAC Assessment: UD0321
ITAC logo
ITAC Assessment: UD0321
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product CORRUGATED CONTAINERS
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 127
Plant Area
n/a
Annual Production 40,000
ton
Production Hrs. Annual 6,900
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,570 4,800,117
kWh
Natural Gas $189,350 46,256
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,355 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,287

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,217 $37,000 $13,167
318,581
kWh
- $1,050
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,310 $7,500 $7,310
157,093
kWh
- -
03 2.1233: Analyze flue gas for proper air/fuel ratio $2,760 $1,100 - $2,760
-
MMBtu
-
04 2.2414: Use waste heat from hot flue gases to preheat $10,068 $14,000 - $10,068
-
MMBtu
-
TOTAL RECOMMENDED $34,355 $59,600 $20,477
475,674
kWh
$12,828
-
MMBtu
$1,050
TOTAL IMPLEMENTED $24,287 $45,600 $20,477
475,674
kWh
$2,760
-
MMBtu
$1,050
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs