ITAC Assessment: UD0310
ITAC logo
ITAC Assessment: UD0310
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product BUSINESS FORMS
NAICS
n/a
SIC 2761: Manifold Business Forms
Sales Range $5
M
to 10
M
# of Employees 140
Plant Area
n/a
Annual Production 4,200
ton
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,760 2,011,723
kWh
Natural Gas $22,976 4,607
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,390 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,265

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8114: Change rate schedules or other changes in utility service $1,258 - $1,258
-
kWh
- -
02 2.6214: Shut off pilots in standby equipment $862 - - $862
-
MMBtu
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $170 - $226
-
kWh
- $(-56.0)
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,326 $442 $950
23,447
kWh
- $376
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $907 $1,800 $1,627
31,360
kWh
$(-720.0)
-
MMBtu
-
06 2.7492: Use proper thickness of insulation on building envelope $4,867 $25,000 - $4,867
-
MMBtu
-
TOTAL RECOMMENDED $9,390 $27,242 $4,061
54,807
kWh
$5,009
-
MMBtu
$320
TOTAL IMPLEMENTED $3,265 $2,242 $2,803
54,807
kWh
$142
-
MMBtu
$320
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs