Assessment Year | 1989 |
---|---|
Principal Product | ENVELOPES |
NAICS |
n/a
|
SIC | 2677: Envelopes |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
n/a
|
Annual Production | 625,000
pieces
|
Production Hrs. Annual | 6,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $151,787 | 2,757,327 |
kWh
|
$0.055 |
Natural Gas | $42,643 | 9,914 |
MMBtu
|
$4.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,594 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4235: Remove or close off unneeded compressed air lines | $1,230 | - |
$980
43,083
kWh
|
- | $250 | |
02 | 2.7494: Install storm windows and doors | $8,782 | $8,000 | - |
$8,782
-
MMBtu
|
- | |
03 | 2.3191: Use demand controller or load shedder | $1,494 | $1,500 |
$1,494
-
kWh
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $2,214 | $1,500 | - |
$2,214
-
MMBtu
|
- | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $874 | - |
$1,594
-
kWh
|
- | $(-720.0) | |
TOTAL RECOMMENDED | $14,594 | $11,000 |
$4,068
43,083
kWh
|
$10,996
-
MMBtu
|
$(-470.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs