| Assessment Year | 1989 |
|---|---|
| Principal Product | PRECISION MACHINED PARTS |
| NAICS |
n/a
|
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 72 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,003 | 1,089,683 |
kWh
|
$0.056 |
| Natural Gas | $7,612 | 1,702 |
MMBtu
|
$4.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,188 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,818 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,855 | $2,800 |
$3,574
64,478
kWh
|
$(-1,719.0)
-
MMBtu
|
- | |
| 02 | 2.3191: Use demand controller or load shedder | $867 | $1,000 |
$867
-
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,928 | $4,920 |
$2,196
41,325
kWh
|
- | $732 | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $332 | - |
$332
13,482
kWh
|
- | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $1,558 | $1,500 |
$1,441
25,791
kWh
|
- | $117 | |
| 06 | 2.2437: Recover waste heat from equipment | $3,648 | $7,000 |
$3,648
60,961
kWh
|
- | - | |
| TOTAL RECOMMENDED | $11,188 | $17,220 |
$12,058
206,037
kWh
|
$(-1,719.0)
-
MMBtu
|
$849 | ||
| TOTAL IMPLEMENTED | $4,818 | $6,420 |
$3,969
80,598
kWh
|
- | $849 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs