ITAC Assessment: UD0304
ITAC logo
ITAC Assessment: UD0304
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product PRECISION MACHINED PARTS
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 72
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 5,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,003 1,089,683
kWh
Natural Gas $7,612 1,702
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,188 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,818

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,855 $2,800 $3,574
64,478
kWh
$(-1,719.0)
-
MMBtu
-
02 2.3191: Use demand controller or load shedder $867 $1,000 $867
-
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,928 $4,920 $2,196
41,325
kWh
- $732
04 2.4231: Reduce the pressure of compressed air to the minimum required $332 - $332
13,482
kWh
- -
05 2.7111: Reduce illumination to minimum necessary levels $1,558 $1,500 $1,441
25,791
kWh
- $117
06 2.2437: Recover waste heat from equipment $3,648 $7,000 $3,648
60,961
kWh
- -
TOTAL RECOMMENDED $11,188 $17,220 $12,058
206,037
kWh
$(-1,719.0)
-
MMBtu
$849
TOTAL IMPLEMENTED $4,818 $6,420 $3,969
80,598
kWh
- $849
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs