Assessment Year | 1989 |
---|---|
Principal Product | ELECT. WIRE ROPE HEISTS |
NAICS |
n/a
|
SIC | 3536: Overhead Traveling Cranes, Hoists, and Monorail Systems |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 1,400
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $171,916 | 2,038,980 |
kWh
|
$0.084 |
Natural Gas | $50,400 | 14,000 |
MMBtu
|
$3.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,985 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,320 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,313 | - |
$2,313
-
kWh
|
- | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $9,236 | - |
$9,636
-
kWh
|
- | $(-400.0) | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,636 | - |
$9,636
-
kWh
|
- | $(-1,000.0) | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,480 | - |
$8,480
-
kWh
|
- | $(-1,000.0) | |
05 | 2.6232: Install set-back timers | $1,252 | - |
$1,448
66,237
kWh
|
$(-508.0)
-
MMBtu
|
$312 | |
06 | 2.7111: Reduce illumination to minimum necessary levels | $1,399 | - |
$1,535
15,533
kWh
|
$(-136.0)
-
MMBtu
|
- | |
07 | 2.7492: Use proper thickness of insulation on building envelope | $1,574 | $5,000 | - |
$1,574
-
MMBtu
|
- | |
08 | 2.7492: Use proper thickness of insulation on building envelope | $1,095 | $7,500 | - |
$1,095
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $32,985 | $12,500 |
$33,048
81,770
kWh
|
$2,025
-
MMBtu
|
$(-2,088.0) | ||
TOTAL IMPLEMENTED | $5,320 | $12,500 |
$2,983
81,770
kWh
|
$2,025
-
MMBtu
|
$312 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs