| Assessment Year | 1989 |
|---|---|
| Principal Product | ELECT. WIRE ROPE HEISTS |
| NAICS |
n/a
|
| SIC | 3536: Overhead Traveling Cranes, Hoists, and Monorail Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 1,400
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $171,916 | 2,038,980 |
kWh
|
$0.084 |
| Natural Gas | $50,400 | 14,000 |
MMBtu
|
$3.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,985 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,320 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,313 | - |
$2,313
-
kWh
|
- | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $9,236 | - |
$9,636
-
kWh
|
- | $(-400.0) | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,636 | - |
$9,636
-
kWh
|
- | $(-1,000.0) | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,480 | - |
$8,480
-
kWh
|
- | $(-1,000.0) | |
| 05 | 2.6232: Install set-back timers | $1,252 | - |
$1,448
66,237
kWh
|
$(-508.0)
-
MMBtu
|
$312 | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $1,399 | - |
$1,535
15,533
kWh
|
$(-136.0)
-
MMBtu
|
- | |
| 07 | 2.7492: Use proper thickness of insulation on building envelope | $1,574 | $5,000 | - |
$1,574
-
MMBtu
|
- | |
| 08 | 2.7492: Use proper thickness of insulation on building envelope | $1,095 | $7,500 | - |
$1,095
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $32,985 | $12,500 |
$33,048
81,770
kWh
|
$2,025
-
MMBtu
|
$(-2,088.0) | ||
| TOTAL IMPLEMENTED | $5,320 | $12,500 |
$2,983
81,770
kWh
|
$2,025
-
MMBtu
|
$312 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs