ITAC Assessment: UD0299
ITAC logo
ITAC Assessment: UD0299
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product DECORATIVE METAL TRIM
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 200
Plant Area
n/a
Annual Production 800,000
lb
Production Hrs. Annual 4,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $121,298 2,111,958
kWh
Natural Gas $27,235 6,313
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,053 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,044

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $7,009 - $7,112
5,275
kWh
$(-103.0)
-
MMBtu
-
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $900 - $900
-
kWh
- -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,667 $750 $1,667
-
kWh
- -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $889 $750 $889
-
kWh
- -
05 2.7141: Lower light fixtures in high ceiling areas $1,588 $1,720 $1,398
27,550
kWh
- $190
TOTAL RECOMMENDED $12,053 $3,220 $11,966
32,825
kWh
$(-103.0)
-
MMBtu
$190
TOTAL IMPLEMENTED $5,044 $3,220 $4,854
27,550
kWh
- $190
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs