ITAC Assessment: UD0297
ITAC logo
ITAC Assessment: UD0297
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product COMMERCIAL ADVERTISEMENT
NAICS
n/a
SIC 3555: Printing Trades Machinery and Equipment
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area
n/a
Annual Production 1,000,000
lb
Production Hrs. Annual 6,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,587 1,169,988
kWh
Natural Gas $1,580 332
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,270 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7226: Use computer programs to optimize hvac performance $1,000 $2,000 $1,000
-
kWh
-
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $807 - $807
-
kWh
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,463 - $1,733
-
kWh
$(-270.0)
TOTAL RECOMMENDED $3,270 $2,000 $3,540
-
kWh
$(-270.0)
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs