| Assessment Year | 1989 |
|---|---|
| Principal Product | METAL PLATING |
| NAICS |
n/a
|
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $5 M to 10M |
| # of Employees | 110 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $277,926 | 4,966,002 |
kWh
|
$0.056 |
| Natural Gas | $168,413 | 44,430 |
MMBtu
|
$3.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,396 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $40,396 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7492: Use proper thickness of insulation on building envelope | $14,040 | $14,400 | - |
$14,040
-
MMBtu
|
- | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $3,566 | $7,000 |
$3,566
98,769
kWh
|
- | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $16,696 | - |
$18,568
-
kWh
|
- | $(-1,872.0) | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,314 | - |
$4,314
-
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $825 | - |
$713
19,050
kWh
|
$(-118.0)
-
MMBtu
|
$230 | |
| 06 | 2.7494: Install storm windows and doors | $955 | $1,920 | - |
$955
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $40,396 | $23,320 |
$27,161
117,819
kWh
|
$14,877
-
MMBtu
|
$(-1,642.0) | ||
| TOTAL IMPLEMENTED | $40,396 | $23,320 |
$27,161
117,819
kWh
|
$14,877
-
MMBtu
|
$(-1,642.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs