| Assessment Year | 1988 |
|---|---|
| Principal Product | AIRCRAFT CARRIER PARTS |
| NAICS |
n/a
|
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 5,400
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $69,139 | 1,291,032 |
kWh
|
$0.054 |
| Natural Gas | $12,556 | 3,160 |
MMBtu
|
$3.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,576 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,433 | - |
$3,733
-
kWh
|
- | $(-300.0) | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $1,143 | - |
$1,387
57,151
kWh
|
$(-244.0)
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $4,576 | - |
$5,120
57,151
kWh
|
$(-244.0)
-
MMBtu
|
$(-300.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs