Assessment Year | 1988 |
---|---|
Principal Product | INDUSTRIAL KNIVES & WAY BARS |
NAICS |
n/a
|
SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
Sales Range | $10 M to 50M |
# of Employees | 137 |
Plant Area |
n/a
|
Annual Production | 2,000
ton
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $185,739 | 3,104,045 |
kWh
|
$0.060 |
LPG | $21,682 | 2,482 |
MMBtu
|
$8.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,599 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,349 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,625 | - |
$2,625
-
kWh
|
- | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,250 | - |
$5,250
-
kWh
|
- | - | |
03 | 2.1332: Convert combustion equipment to burn natural gas | $10,439 | $4,448 | - |
$(-11,243.0)
-
MMBtu
|
$21,682
-
MMBtu
|
|
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,285 | $552 |
$1,642
16,706
kWh
|
$(-357.0)
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $19,599 | $5,000 |
$9,517
16,706
kWh
|
$(-11,600.0)
-
MMBtu
|
$21,682
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,349 | $5,000 |
$4,267
16,706
kWh
|
$(-11,600.0)
-
MMBtu
|
$21,682
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs