Assessment Year | 2012 |
---|---|
Principal Product | Industrial Organic Chemicals |
NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 156 |
Plant Area |
2,003,760
ft2
|
Annual Production | 36,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,278,779 | 30,943,249 |
kWh
|
$0.074 |
Electricity Demand | $559,728 | 47,255 |
kW-mo/yr
|
$11.84 |
Electricity Fees | $106,656 | - |
|
- |
Natural Gas | $1,603,321 | 277,341 |
MMBtu
|
$5.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $302,325 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $85,074 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $78,730 | $63,811 |
$64,540
872,159
kWh
|
$14,190
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $71,478 | $47,240 |
$58,595
791,822
kWh
|
$12,883
-
kW-mo/yr
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $53,118 | $2,520 | - | - |
$53,118
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $25,712 | $21,000 |
$21,081
284,877
kWh
|
$4,631
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $21,901 | $1,660 |
$17,952
242,596
kWh
|
$3,949
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,917 | $6,660 |
$16,328
220,649
kWh
|
$3,589
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,529 | $8,200 |
$10,267
138,747
kWh
|
$2,262
-
kW-mo/yr
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,055 | $80 |
$7,593
102,606
kWh
|
$2,462
-
kW-mo/yr
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,885 | $13,800 |
$7,286
98,456
kWh
|
$1,599
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $302,325 | $164,971 |
$203,642
2,751,912
kWh
|
$45,565
-
kW-mo/yr
|
$53,118
-
MMBtu
|
||
TOTAL IMPLEMENTED | $85,074 | $4,260 |
$25,545
345,202
kWh
|
$6,411
-
kW-mo/yr
|
$53,118
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs