ITAC Assessment: UD0264
ITAC logo
ITAC Assessment: UD0264
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product CUSTOM METAL FABRICATION
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area
n/a
Annual Production 8,000,000
lb
Production Hrs. Annual 4,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,369 409,730
kWh
Natural Gas $9,082 2,030
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,273 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,393

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $677 - $1,108
42,497
kWh
$(-431.0)
-
MMBtu
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $880 $1,200 $1,278
12,603
kWh
$(-398.0)
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,732 $3,790 $1,597
28,722
kWh
$(-145.0)
-
MMBtu
$280
04 2.7494: Install storm windows and doors $984 $929 - $984
-
MMBtu
-
TOTAL RECOMMENDED $4,273 $5,919 $3,983
83,822
kWh
$10
-
MMBtu
$280
TOTAL IMPLEMENTED $3,393 $4,719 $2,705
71,219
kWh
$408
-
MMBtu
$280
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs