ITAC Assessment: UD0262
ITAC logo
ITAC Assessment: UD0262
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product PLASTIC PACKAGING
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area
n/a
Annual Production 8,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $214,063 5,441,090
kWh
Natural Gas $7,440 1,472
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,912 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,844

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $13,844 $17,000 $13,844
-
kWh
- -
02 2.7111: Reduce illumination to minimum necessary levels $794 $60 $714
15,826
kWh
- $80
03 2.2437: Recover waste heat from equipment $6,565 $18,000 - $6,565
-
MMBtu
-
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,829 - $4,829
-
kWh
- -
05 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads $7,880 $5,000 $7,880
149,179
kWh
- -
TOTAL RECOMMENDED $33,912 $40,060 $27,267
165,005
kWh
$6,565
-
MMBtu
$80
TOTAL IMPLEMENTED $13,844 $17,000 $13,844
-
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs