ITAC Assessment: UD0251
ITAC logo
ITAC Assessment: UD0251
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product POWER SYSTEMS
NAICS
n/a
SIC 3612: Power, Distribution, and Specialty Transformers
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 700
pieces
Production Hrs. Annual 2,080
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $116,798 1,818,875
kWh
Natural Gas $4,749 839
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,103 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,657

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8114: Change rate schedules or other changes in utility service $9,500 $15,000 $10,332
-
kWh
- $(-832.0)
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $7,275 - $7,275
-
kWh
- -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,853 $16,000 $5,407
62,134
kWh
$(-1,554.0)
-
MMBtu
-
04 2.5194: Redesign process $2,282 $1,500 $2,454
27,550
kWh
$(-172.0)
-
MMBtu
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $882 $300 $922
12,603
kWh
$(-40.0)
-
MMBtu
-
06 2.6224: Schedule baking times of small and large components $311 $500 $311
4,982
kWh
- -
TOTAL RECOMMENDED $24,103 $33,300 $26,701
107,269
kWh
$(-1,766.0)
-
MMBtu
$(-832.0)
TOTAL IMPLEMENTED $17,657 $15,300 $18,529
12,603
kWh
$(-40.0)
-
MMBtu
$(-832.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs