ITAC Assessment: UD0248
ITAC logo
ITAC Assessment: UD0248
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product PAPER BOXES
NAICS
n/a
SIC 2652: Setup Paperboard Boxes
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area
n/a
Annual Production 1,800,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,887 1,001,172
kWh
Natural Gas $51,564 11,401
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,377 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,345

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8112: Combine utility meters $1,427 - - - $1,427
02 2.8114: Change rate schedules or other changes in utility service $7,032 $10,000 $7,032
-
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,309 $400 $2,149
24,326
kWh
- $160
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,845 $360 $1,354
18,171
kWh
$(-223.0)
-
MMBtu
$714
05 2.7492: Use proper thickness of insulation on building envelope $4,094 $6,880 - $4,094
-
MMBtu
-
06 2.7494: Install storm windows and doors $6,670 $4,038 - $6,670
-
MMBtu
-
TOTAL RECOMMENDED $23,377 $21,678 $10,535
42,497
kWh
$10,541
-
MMBtu
$2,301
TOTAL IMPLEMENTED $16,345 $11,678 $3,503
42,497
kWh
$10,541
-
MMBtu
$2,301
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs