Assessment Year | 1987 |
---|---|
Principal Product | FLUOROPOLYMER PRODUCTS |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $259,740 | 5,063,892 |
kWh
|
$0.051 |
Natural Gas | $89,880 | 18,581 |
MMBtu
|
$4.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $45,830 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $2,394 | $200 |
$2,394
102,872
kWh
|
- | - | |
02 | 2.2444: Use hot process fluids to preheat incoming process fluids | $1,466 | $3,000 | - |
$1,466
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,505 | $1,790 |
$3,176
75,615
kWh
|
- | $329 | |
04 | 2.4133: Use most efficient type of electric motors | $697 | $2,000 |
$697
15,826
kWh
|
- | - | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $12,129 | - |
$12,129
-
kWh
|
- | - | |
06 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $5,305 | $67 |
$472
20,223
kWh
|
$4,833
-
MMBtu
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,948 | $4,140 |
$1,770
42,204
kWh
|
$12,178
-
MMBtu
|
- | |
08 | 3.4151: Minimize water usage | $3,986 | $2,000 | - | - | $3,986 | |
09 | 3.4115: Recover and reuse cooling water | $2,400 | $4,000 |
$(-369.0)
(-7,327)
kWh
|
- | $2,769 | |
TOTAL RECOMMENDED | $45,830 | $17,197 |
$20,269
249,413
kWh
|
$18,477
-
MMBtu
|
$7,084 | ||
TOTAL IMPLEMENTED | $45,830 | $17,197 |
$20,269
249,413
kWh
|
$18,477
-
MMBtu
|
$7,084 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs