Assessment Year | 1987 |
---|---|
Principal Product | WELDING WIRES & FLUXES |
NAICS |
n/a
|
SIC | 3398: Metal Heat Treating |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 3,600,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $369,892 | 5,623,095 |
kWh
|
$0.066 |
Natural Gas | $54,667 | 10,639 |
MMBtu
|
$5.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,278 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,281 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $26,035 | $30,000 |
$32,616
577,081
kWh
|
$(-6,581.0)
-
MMBtu
|
- | |
02 | 2.3212: Optimize plant power factor | $4,712 | $12,000 |
$4,712
-
kWh
|
- | - | |
03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,245 | - |
$1,844
53,634
kWh
|
$(-599.0)
-
MMBtu
|
- | |
04 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $534 | $6,000 |
$422
12,309
kWh
|
- | $112 | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,752 | - |
$7,152
-
kWh
|
- | $(-1,400.0) | |
TOTAL RECOMMENDED | $38,278 | $48,000 |
$46,746
643,024
kWh
|
$(-7,180.0)
-
MMBtu
|
$(-1,288.0) | ||
TOTAL IMPLEMENTED | $31,281 | $48,000 |
$37,750
589,390
kWh
|
$(-6,581.0)
-
MMBtu
|
$112 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs